Panel Information
| Barcode | 6510-EX-20-GF |
| Panel Number | EX-20-GF |
| Site | Cefn Cribwr_BL_PL3-6_GF_EX (#6510) |
| Plot | 3-6 |
| Position | EX |
| Floor | GF |
| Block | — |
| Length | 2580 mm |
| CDT File | Z:\6510_Cefn Cribwr_BL_PL3-6_GF_EX\6510_Cefn Cribwr_BL_PL3-6_GF_EX---140-2603\FRAMEEX-20-GF.CDT |
| Status | Complete |
| Created | 02/10/2026 11:42:21 |
| Completed | 05/10/2026 08:03:31 |
Station Timeline
Framing Station
Printed: 11:42:21
Insulation Boarding
Not yet reached
Nailing Bridge
Arrived: 12:35:25
· Left: 14:03:22
· 5276s
Paper Application
Arrived: 14:03:22
· Left: 08:03:31
· 237609s
Panel Flipping
Not yet reached
Insulation Filling
Not yet reached
OSB Glue Application
Not yet reached
Paper Application 2
Arrived: 09:13:49
· Currently here
Exit Line to Windows
Not yet reached
All Scan Events
3 total
| Time | Station | Scanner | Barcode | Type |
|---|---|---|---|---|
| 12:35:25 | Nailing Bridge | Scanner 2 | 6510-EX-20-GF | Entry |
| 14:03:22 | Paper Application | Scanner 3 | 6510-EX-20-GF | Entry |
| 09:13:49 | Paper Application 2 | Scanner 7 | 6510-EX-20-GF | Entry |